ZB ZB
Live now
Start time
Playing for
End time
Listen live
Listen to NAME OF STATION
Up next
Listen live on
ZB

Government document dump: KiwiRail's suitability to run Interislander questioned

Author
Georgina Campbell and Thomas Coughlan,
Publish Date
Fri, 10 May 2024, 2:21PM

Government document dump: KiwiRail's suitability to run Interislander questioned

Author
Georgina Campbell and Thomas Coughlan,
Publish Date
Fri, 10 May 2024, 2:21PM

Ministry of Transport officials have raised the question of KiwiRail’s suitability to run the Interislander business in the long term and have suggested it could be separated into another State-Owned Enterprise (SOE) or sold.   

The Government refused to give KiwiRail more money for the mega ferries soon after it came to power - leaving the plan to replace the ageing Interislander fleet dead in the water.   

Overall costs, including new terminals and wharf upgrades, had ballooned to almost $3 billion.   

The decision, announced by Finance Minister Nicola Willis, sent a sharp warning to the public sector that the Government is not afraid to shake up projects that may have previously been presented as a fait accompli.   

Requests made by the Herald under the Official Information Act for documents relating to the decision have previously been declined because they would soon be proactively released. These documents have been released today by the Treasury.   

Documents include the letter Willis sent to KiwiRail relaying the Government’s decision.   

They also reveal some of the alternative options floated and more about the question of KiwiRail’s suitability to run the Interislander business.   

Questions over whether KiwiRail should run Interislander 

Ministry of Transport officials provided the Government with alternative options to the mega ferries in a briefing on December 6.   

In the short to medium term, KiwiRail would need to decide if it could or should extend the life of its two existing non-rail-enabled ferries or buy or lease second-hand ferries.   

“This could buy KiwiRail time while it decides whether to purchase new ferries with reduced landside requirements. (It would likely take at least 5 years to plan, design, procure and bring into service new ferries).”   

KiwiRail could consider further extending the life of its only rail-enabled ferry, Aratere, by making it a freight-only service.   

In KiwiRail’s view, proceeding without rail-enabled ships was not an option it was willing to consider, officials said, while also noting KiwiRail was not prepared to pay for this.   

However, officials did not consider this would make a material difference to the amount of freight that would move from road to rail.   

A relatively small proportion of total rail freight was carried across Cook Strait and almost all of it could be done by road bridging. This is where containers are moved from trains by a vehicle that loads them onto the ferry.   

This is standard practice around the world, officials said.   

“Which is invisible to KiwiRail customers, and who are likely to be indifferent about how their goods are moved onto the ferry.”   

The difficulties KiwiRail has had with the mega ferry project, along with core rail issues it faces, raised the question of KiwiRail’s suitability to run the Interislander business in the medium to long term, officials said.   

“The Interislander business could be separated into another State-Owned Enterprise or sold via a trade sale, they said.   

“KiwiRail would be expected to contract with this business to provide freight services across the Cook Strait, but how this is achieved would be left as a commercial decision between parties.”   

Finance Minister Nicola Willis said the Government was concerned about continued significant cost blow-outs. Photo / Mark Mitchell. 

Finance Minister Nicola Willis said the Government was concerned about continued significant cost blow-outs. Photo / Mark Mitchell.   

Officials said KiwiRail was incentivised to make cancelling the contract for the mega ferries as unattractive as possible and had suggested the break fee to do so could be high.   

“But KiwiRail have also acknowledged that ferry prices have increased significantly since they signed their fixed price contract, so it is conceivable the ferries could be sold on for a price that does not result in such high losses.”   

Officials said it was plausible that if a new approach was adopted, especially by someone other than KiwiRail, then a more commercially viable option should be possible.   

“Even if significant government support is required resetting, now could provide a more open and transparent process.   

“This would allow all parties to access any required subsidy and for the Government to be very clear about what it is purchasing.”   

What Finance Minister Nicola Willis told KiwiRail 

In a letter dated December 12, Willis wrote to KiwiRail chairman David McLean saying she would not be providing additional cash and was rescinding an “in-principle decision” made by Labour to increase tagged contingency funding by $750 million.   

This meant Cabinet had confirmed that Crown funding was “limited to $435.1m in appropriated funding (of which approximately $63 million remains), she said.   

Willis said she understood this decision meant the “KiwiRail Board may likely decide that the only viable way to proceed is to exit Project iRex” [the technical name given for the ferry replacement project]”. 

She said KiwiRail would need to engage with the Ministry of Foreign Affairs and Trade and Treasury on negotiating any potential exit from ferry contracts.  

Willis said the Government was concerned about the “continued significant cost blow-outs” and the “changing nature of the investment” the Crown was being asked to make.   

“The cost has since escalated to be projected at approximately $3 billion - around four times its original cost,” Willis wrote.   

She added her concern that “only 21 per cent of these costs related to the core project of replacing ageing ferries. The project has become more of a landslide infrastructure project than a new ferries project”.   

She said the risk of cost escalations had “reduced our confidence” in the project.   

KiwiRail warns existing ferries may not be able to serve for much longer 

McLean wrote back on December 15, saying the Government would “wind down” the iRex project “as we cannot proceed without further Government funding”.   

McLean said KiwiRail was making arrangements to exit iRex although he did not detail what this may entail. He appeared to ask for some distance between KiwiRail and the Minister.   

“[T]hese are commercial contractual matters between KiwiRail and other parties.   

“We do not wish to implicate the Ministries in a contractual relationship, and it is important that we maintain good faith relationships between contractual partners by allowing these parties to negotiate directly,” he said. 

“We will be guided by our primary legal duty as directors to act in the best interests of the company, which should be congruent with the interests of you as shareholder and New Zealand taxpayers,” he said. 

The board would meet in future to discuss future options, McLean said. 

These options would need to “incorporate investment in both replacement ferries and necessary landside infrastructure” to “accommodate projected future growth in freight and passenger demand over the life cycle of the assets” and to “recognise that the existing ferries, and existing wharf infrastructure, must be replaced in the near term”. 

The letter warned the existing ferries may not be able to serve for much longer.  

“We will be assessing the potential length of service for the existing ships as part of the forward options assessment,” Mclean said.  

“We had planned to continue using the existing fleet for another 2-3 years, until new ferries arrive. While we plan to do what we can to enable these aged vessels to continue to operate safely and reliably, it is important that this 2-3 year period is used to plan for a long-term replacement fleet.”   

Thomas Coughlan is Deputy Political Editor and covers politics from Parliament. He has worked for the Herald since 2021 and has worked in the press gallery since 2018.   

Georgina Campbell is a Wellington-based reporter who has a particular interest in local government, transport, and seismic issues. She joined the Herald in 2019 after working as a broadcast journalist. 

Take your Radio, Podcasts and Music with you